The v2019pre release cycle started in April 2019.

Milestone

Date

Start of release cycle

2019-04-01
2019-04-15

Soft feature freeze: end of feature proposal and review period

2019-05-21

Soft code freeze/hard feature freeze: end of feature development for this release, only bugfixes allowed

2019-06-04

Release candidate 1 (RC1)/hard code freeze: no new code changes may be made after this date

2019-06-11 EOD

RC testing

2019-06-12..25

v2019pre release

2019-06-26

If the release candidate 1 does not successfully pass all required tests, then the issues will be fixed and a new release candidate will be re-tested. This would delay the release, which would be reflected on this page.